PMI PMI-ACP Dumps

PMI PMI-ACP Dumps

PMI Agile Certified Practitioner (PMI-ACP)
  • 214 Questions & Answers
  • Update Date : October 10, 2024

PDF + Testing Engine
$65
Testing Engine (only)
$55
PDF (only)
$45
Free Sample Questions

What makes Pass4sureClub the optimal selection for certification exam preparation?

Pass4sureClub offers PMI PMI-ACP practice test questions along with answers, unlike other online platforms. To access the entire review material, you need to create a free account on Pass4sureClub. Many customers worldwide are achieving high scores using our PMI-ACP Dumps. You can also get a 100% pass guarantee and a money-back guarantee for the PMI-ACP exam. PDF files are available for download immediately after purchase.

An Essential Resource for Preparing for the PMI PMI-ACP Exam:

Pass4sureClub is the ultimate resource for preparing for the PMI PMI-ACP exam. We strictly follow the precise review test questions and answers, which are consistently updated and verified by experts. Our team of PMI PMI-ACP exam dumps experts, hailing from various reputable backgrounds, are knowledgeable and skilled individuals who have thoroughly reviewed a significant portion of PMI PMI-ACP exam questions and answers to assist you in grasping the concepts and passing the certification exam with high marks. PMI PMI-ACP braindumps are the most efficient method to prepare for your exam in just 1 day.

Mobile-Friendly and Easily Accessible for Users:

Accessible and User-Friendly on Mobile Devices. Our platform for the PMI PMI-ACP exam is designed to be incredibly easy to use. The primary objective of our platform is to provide the latest, accurate, updated, and highly beneficial review material. Students can utilize this material to study and effectively navigate the implementation and support of Salesforce systems. Authentic test questions and answers are accessible, with PDF downloads available immediately upon purchase. With an internet connection on your mobile device, you can conveniently study on our mobile-friendly website.

Industry Experts Have Verified PMI PMI-ACP Dumps:

Gain Immediate Access to the Latest and Precise PMI PMI-ACP Questions and Answers:
Our exam database is regularly updated throughout the year to incorporate the latest PMI PMI-ACP exam questions and answers. Each test page displays the date at the top, along with the updated list of exam questions and answers. With the authenticity of the current exam questions, you will successfully pass the exam on your first attempt.

The PMI PMI-ACP exam dumps have been verified by dedicated industry professionals, ensuring accurate PMI PMI-ACP test questions and answers with brief explanations. Each question and answer is scrutinized by experts from Salesforce, individuals with extensive professional experience in the vendor's examination.

Pass4sureClub.com stands out by offering the best PMI PMI-ACP exam questions along with detailed explanations, unlike many other exam portals.

Pass4sureClub.com is dedicated to delivering top-notch PMI PMI-ACP braindumps that will assist you in passing the exam and obtaining certification. To ensure the most effective preparation method for the PMI PMI-ACP exam, we offer up-to-date and realistic test questions sourced from current exams. If you purchase the complete PDF file but do not pass the vendor exam, you are eligible for a refund or exam replacement. For further details about our clear-cut money-back guarantee, please visit our guarantee page.

Related Exams


PMI PMI-ACP Sample Questions

Question # 1

An experienced product owner presents the epics and corresponding stones during a release planning session with the established team The executive sponsor asks the team when the features will he delivered What should the agile team do?

A. Evaluate how much can be delivered based on the Scrum Master's estimation
B. identify a set of user stored based on the team's velocity
C. initiate an estimation session
D. Consult historical data for project completion



Question # 2

During a review session an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value What should the team have done to prevent this?

A. Reprioritized requirements prior to committing to iteration work
B. Ensured that requirements remained stable during the iteration cycle
C. Had stakeholders focus on items created after the product backlog was initially built
D. Worked on features rather than a set of components



Question # 3

On what should an agile team work to achieve predictable flow?

A. Small user stories
B. Simple acceptance criteria
C. Lean features
D. Lean backlogs



Question # 4

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted there is no value to the customers during this iteration What must the agile practitioner do? 

A. Add the new change request as a new user story in the product backlog for the upcoming iteration
B. Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
C. Recommend cancelling the current iteration and plan the change request into the next iteration 
D. Recommend that the product owner add this change request as a user story to me backlog tor the current aeration 



Question # 5

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stones into the iteration backlog What should the team do first to define the tasks needed to implement the user stories?

A. Self-organize
B. Assign tasks to each team member
C. Meet with me customer
D. Identify the Scrum Master



Question # 6

A senior team member feels underutilized. What should the agile practitioner do?

A. Transfer the senior member to another team that will more fully utilize their skill set.  
B. Conduct a performance evaluation to determine whether or not this member is a team player. 
C. Encourage the project team to involve the senior member in more project activities.  
D. Ask the functional manager to determine the best course of action.  



Question # 7

A learn using Kanban identifies mat their cycle time has significant variation After brainstorming, the team determines that the root cause is the stones' varying sizes and risks What should the team do?

A. Reduce work in progress (W1P) limits to accommodate slack for riskier stories
B. Create a triage step on the Kanban board to pre-identify risky stones
C. Set a policy lo break down stories larger than a specified complexity, then adjust the WIP
D. Create a dedicated overflow swimlane on the Kanban board for stones that are loo large



Question # 8

A project team identifies a number of technical challenges with features in the next sprint. What should they do?

A. Request direction from the technical manager.
B. Encourage the product owner to reallocate the features to another sprint.
C. Determine who is best qualified to address the challenges.
D. Ask the product owner to assign the tasks to the most appropriately skilled resources.



Question # 9

What should an agile practitioner do to ensure that the end product meets business requirements? 

A. Invite the team to iteration review meetings  
B. Obtain agreement from the product owner on business requirements
C. Request that regular reports are sent to stakeholders
D. Confirm managers and stakeholders are invited to product review meetings.



Question # 10

A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.What should be proposed to the team? 

A. Have other team developers attend training to learn database skills.
B. Monitor the retrospectives of two additional sprints before taking action.
C. Plan fewer stories for the sprint to reduce the database engineers' workload.
D. Ask the scrum master to work with the product owner to remove backlog stories that have database dependency.



Question # 11

During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do? 

A. Add this threshold requirement request as acceptance criteria in all impacted stories  
B. Create a spike story to analyze the impact of the threshold requirement on current stories 
C. Conduct design planning session to review the performance threshold requirement  
D. Identify the tasks for the new performance threshold requirement  



Question # 12

A project is starling and the type of wont is complex and suitable for agile in assessing the learn members it appears that co-location would be a challenge.What should the agile practitioner do? 

A. Select and implement collaboration tools to augment team interactions  
B. Provide each geographical area with their own product owner and divide the work between the teams 
C. increase the number of requirements documents and ensure they are dearly communicated 
 D. After several sprints calcuate velocity based on primary learn location and use secondary team as reserve



Question # 13

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.What should the agile coach do?

A. Work with the team to determine points at which to celebrate its work.
B. Provide the team with a break by scheduling a team event.
C. Have the team increase work in progress (WIP) levels to more quickly complete the flow.
D. Rejuvenate the team by temporarily reducing WIP levels.